Finally breaking ground!

started mine by hand but over 375 ft of hard ground I got a trencher and completed that that was over 30 years ago was I was much younger and in better health ,yours looks very good nice job :thumbsup:
 
Been slacking on this project due to the holidays. It's been insulation, insulation, insulation! I framed in the area at the top of the stairs and got it all insulated. I can finally say I am ready to sheet this whole thing in OSB!


IMG_0939.JPG
IMG_0952.JPG
 
The interior is sheeted. Yes I went with OSB. It will be a working garage. Prime and paint next week if its warm enough. Then I will install firestop drywall on the lower 4' perimeter so I can weld away.

Getting close to move in time! Wife wants the other garage for her woodworking equipment so I'm under pressure!
IMG_0979.JPG
IMG_0980.JPG
IMG_0981.JPG
 
Looks good now....almost time to start with making it messy - working on cars. :thumbsup:

Yes Sir, that is the plan. I have a Power Wagon to finish and a 71 SE to build!
 
Getting close to move in time!

IMG_0992.JPG
IMG_0993.JPG
 
We have daylight! After looking at the costs of LED fixtures that are decent I was overwhelmed at the cost. I need 24 for the first floor. I went with a standard T8 wrap from Lowes and GE 6500k LED tubes. Buying the bulbs in 16 packs and my military discount got the price to $24 per fixture.

IMG_1026.JPG


I also got the network done. The place is wired, network, TV, Stereo, and more.

IMG_1010.JPG


Started on the black iron air lines. There will be 2 drops on the back wall and one on the front.

IMG_1023.JPG


My makeshift pipe vise. I wouldn't try it with anything bigger than 1" though.

IMG_1021.JPG
 
Got the 50" 4K HDR TV with soundbar up And built the workbench this weekend. I have wood putty soaking into all the imperfections on the top and will sand and stain then 3 coats of poly on the top.

IMG_1035.JPG
IMG_1039.JPG
 
get some 10gauge steel for part of your bench so you have a place to do what will wreck the nice wood
 
Did 6 coats of poly on the workbench after stain. Installed the HVAC, went with a 36k Mitsubishi split system, summer is coming and my neighbor has decided where he will hangout on the weekends! Fridge is up and running and I am moving in!

IMG_1062.JPG
IMG_1047.JPG
IMG_1046.JPG
 