oldbee
Well-Known Member
Did you try any of that slick-ease(?) or some such for pulling wires? Used to use it when making wire conduits on buses. Don’t remember the name, but it was like lard consistency and would slowly evaporate.
Lookin good.So Sorry - It has been a while - just dreading this Electrical Inspection . . .
Work is progressing - slowly - and it's ALL my fault as I'm dragging my feet with the electrical
due to my fear of the electrical inspection . . . but still making progress on the task
Got all of the lower floor bay work done - and the light outlets . . .
Got this work done on the silo - once I figured out what light that were getting installed . . . They are just Deck
lights - but they hug the wall and thought that prevent them from getting bumped all the time . . . maybe ? ? ?
This is the first light . . .
View attachment 1865588
And the second light getting installed . . . appears that the 6 lights in the kit will work out just fine too !
View attachment 1865589
Working my way up the spiral staircase and really liking the results . . .
View attachment 1865590
And, when it was finished, the view from the top was awesome . . .
View attachment 1865591
Getting dark outside so I checked out the lighting from the shop - happy with the results !
View attachment 1865592
Not all work and no play . . . Obie bumped into this guy and he was not too happy, he went into "protect" mode
and attacked it - had to pull him off the King Snake and prevent him from hurting the guy - he's a very GOOD
snake to have around - and he's a BIG one to boot !
View attachment 1865593
There were a group of these at a local eatery - and they all left together - was only able to get a pic when we
came to a stop - they were all pretty cool !
View attachment 1865594
And - finally got the truck in to work on the bent frame from the accident - when the Toyota Tacoma drove
ringht into the back of the truck on the interstate . . . at least the receiver is now level - not pointing down . . .
View attachment 1865595
And now working on getting all of the electrical circuits into the can and getting all of the circuit breakers
installed to handle them . . . moving along . . .
View attachment 1865596
And working on trying to make sure that the wiring in the shop looks respectable for the inspection too
View attachment 1865597
Yeah - dragging my feet but finally realizing that it needs to get done so I'm pushing myself a bit harder
to get this thing done and just fix anything that was done wrong and move on . . .
More Later . . .
The biggest problem I have seen people make is using a counduit that is too tight for the cable run, and too many bends.Did you try any of that slick-ease(?) or some such for pulling wires? Used to use it when making wire conduits on buses.




California uses permits as a way to build wealth... Theirs, not yours...Wow, sounds like you dodged a bullet with the permit stuff. If they would have found something they didn't like you could have been in trouble!
I had my township come out to inspect the street related area in order to repave our street. They found a drain I had going through the curb (been there for 25 years). Well, that wasn't legal so it had to be removed. I told them my basement would flood if it was. They didn't care. Anyway, long story short: $16,000 later it is removed and my basement still has an appropriate drain. Ouch! That was a bill I wasn't expecting or wanted!
Back to your place: It looks great and obviously, having passed the inspections, was built well - but we already knew that.
Well done![]()
Hurry up and wait, always the way!Well, well now - one step forward - 16 steps backwards . . . Sheeesh . . .
Unbelievable - is all that I can say . . . was ready to get the electrical inspection . . .
Inspector asked - where's your building inspection . . .
Building inspection - there was a building here - it was just made larger
- "thought" that it was grandfathered and no needed ( it is also unincorporated area )
Apparently not so . . . call the building inspector that comes out and views the building
He's impressed - says I don't see a problem . . . go get a building permit downtown - OK !
Go downtown - get in line to get my building permit . . . she asks - where your zoning permit ?
UH - what ? ?
Go next door and get your zoning permit . . .okay . . .
Go next door - ask about getting a zoning permit - ok - do you have well and septic there ?
Yes . . . hands me a piece of paper - call these people and get a well/septic assessment . . .
Call them . . . they give me a website with 10 pages of items that need to be done.
- near the end - you have to call 811 and get all your power lines marked FIRST . . .
Call them - they will be out in 3 days - latest . . . show up on day 3 - mark the wires
( P.S. - NO where even CLOSE to the septic ( and I knew that ) . . .
I'll submit this - and my boss will take up to 2 weeks to reply ? ? ? 2 Weeks ? ? ?
Sheesh . . .
Finally - get that approved, back downtown, to get the zoning permit . . .
How tall is the building - 18 feet -ish . . . it needs to be 20' from the back property line
- and 10 feet from the side property line . . . ( I think I'm covered )
Finally get the zoning permit - go next door and get the building permit.
Call the inspector back - got my permit - can you come out and inspect the building now ?
Busy today - how about Monday - I'll have to take time off work on Monday to meet with you.
He ends up showing up that day - inspects the building - passes everything.
Spent a week working on electrical stuff - to get ready for spray foam insulation . . .
- was supposed to be done 2 weeks ago - got delayed and pushed to last Friday . . .
- last Friday - got delayed - and pushed to NEXT Friday . . .
So that's where we now stand - spray foam ( 3/4 of the building on Friday )
- then I have to empty the last part of the shop - and have them back to finish it.
Got this knee wall don on the other side of the upstairs . . . and got outlets installed too.
View attachment 1937573
This is how the stuff will get UP there into the shop . . . got the doors hung on the hinges . . .
View attachment 1937574
Turned out pretty good - got a bit of work to do to get them to open/close smoothly . . .
View attachment 1937575
But they can be opened and closed . . . wit a bit of effort . . .
View attachment 1937576
Getting ready to get started on the lean-to the will be going on the side of the other building - here . . .
View attachment 1937577
Got everything done and ready for spray foam . . . excited to get it done . . .
Then all the sheetrock needs to be installed - and get the final electrical inspection . . . and then get Duke Power
out to hook up my power . . .
Been a while in the process . . . but "think" it's FINALLY getting to the final part . . . Sheeesh . . .
More Later . . .