Shop plans finally coming together!

1KoolBee

Well-Known Member
Local time
11:58 AM
Joined
Sep 30, 2021
Messages
410
Reaction score
588
Location
Northern ID
So after being “shopless” for over 10 years, the dream is back on track. Corners are in. Should have all the poles set by end of the week.

IMG_5608.jpeg
 
Awesome! Good luck!
 
I Put my pole garage up 30 years ago. Built allot cars in it.

I call it my " Dog House"

Good luck.
the best feeling is building cars in it while it rains and snows outside.

:thumbsup:
 
I Put my pole garage up 30 years ago. Built allot cars in it.

I call it my " Dog House"

Good luck.
the best feeling is building cars in it while it rains and snows outside.

:thumbsup:
Thanks guys! Given that I live in North Idaho, the ability to build in the winter will be awesome!
 
building a shop is as much fun as working in it!
 
Like 493 Mike said, think seriously about it. Talk to your concrete contractor about it as a lot of them are installing the tubing themselves now. Even if you don't hook the system up right now it will be there when you are ready. Good luck and have fun with it.
 
Agreed on the radiant floor heat. There is a company on the west coast called BlueRidge Company (blueridgecompany.com) that has great pricing and excellent customer service. They will design the system for you if you provide a floor plan, and then give you a bill of material for everything. I dealt with them on my house and also my shop and have very pleased with working with them. If you buy enough from them, the shipping is free.

It doesn't cost much to get the tubing in the floor...you can buy the expensive stuff later. On my shop, I put visqueen down, then 3" foamboard and stapled the tubing directly to the foamboard and then wire mesh on top of that and poured concrete. In the house, I attached the tubing to the wire mesh and had less insulation below the concrete. The wire mesh/tubing are pulled up mid concrete in the house....but the contractor did not cut the concrete. In the garage they cut the concrete because they knew the tubing was 4" down.
 
Thanks for the tip but funding this is a stretch for me since I’m hiring out the labor. I’ll probably put the $ into insulation and I’ll use the wood stove I never installed in my previous shop .
 
i went with lots of insulation and a gas hanging furnace. 100,000 btu. My shop is 24x40 with a 12 foot ceiling. I was told it was to big and would be inefficient. The themostat is set at 45. The heat is always on. When I go out it takes less than 10 minutes to warm up. I'm in the shop nearly every day. It didn't increase our gas bill by more than $50-$75 a month.
Doug

17714.jpeg
 
I have a Hot Dawg heater in my garage. To put one in the shop I’d have to trench a gas line over 100’ or install a propane tank. Maybe a future upgrade
 
So we’re setting poles right now. This 3 point cement mixer is real handy. One load sets one pole. Hydraulic top link makes dumping easy. Have to run the engine at idle to keep from spinning drum too fast.

IMG_5609.jpeg
 
Last edited:
This weeks progress, 18 poles set, 4 to go. 2-1/2 pallets of 80 lb bags. Good thing we had a couple 20 year olds working for us!! Frame out next week.

IMG_5610.jpeg
 